Engineering for LNG Terminals

Bangladesh


Project Owner

Petrobangla (Bangladesh Oil, Gas & Mineral Corporation)

Project Name

Techno-Economic Feasibility Study, Engineering Services and Tender Management Services for Construction of a Land Based LNG Terminal at Matarbari, Cox's Bazar

Completion Date

January 2023 (Scheduled)

Terminal Design Capacity

7.5 MMTPA

Scope of Work

TGES was awarded the FS, Engineering Services and Tender Management Services
1. Field Data Collection
2. Techno-economic Feasibility Study
3. Environmental Impact Analysis Study (EIA)
4. Relocation and Resettlement Study
5. Pre-Front End Engineering Design (Pre-FEED)
6. RFP Document for Selecting Terminal Developer on BOOT Basis
7. Project Cost Estimate with Financial & Economic Analysis
8. Tender Management Services and Bid Proposal Evaluation for Selecting Terminal Developer on BOOT Basis

Taiwan


Project Owner

CPC Corporation, Taiwan

Project Name

FEED for an expansion project of its LNG receiving terminal at Yung An, ROC

Completion Date

August 2020

Scope of Work

TGES was awarded the front end engineering design (FEED) for an expansion project of Yung An LNG receiving terminal
1. Basic design including process line-up, equipment sizing, layout, specifications etc.
2. Geotechnical survey
3. Compilation of technical specification for Re-gasification facilities EPC and Tank EPC

Source of the Photo: https://en.cpc.com.tw/Default.aspx

Thailand


Project Owner

PTT LNG Company Limited

Project Name

PTTLNG Company Limited Project Management and Engineering Consultancy Services for LNG Receiving Terminal Expansion Project (Phase II)

Completion Date

March 2017

Terminal Design Capacity

10 MMTPA

Scope of Work

PMC (Project Management Consultant)
:Perform Project Management for all of activities by EPC contractor (Engineering, Procurement, Construction, Commissioning) on behalf of Project Owner including :

  • Review, verify, assess, analyze EPC deliverables
  • Schedule Monitoring, Assessment and suggest recovery plan, if required
  • Health, Safety and Environment (HSE〕, monitoring and management
  • Quality Assurance and Quality Control 〔QA/QC〕
  • Construction management including Pre-Commissioning, Commissioning support
  • Operational optimization and trouble shooting in initial stage of operation
  • Provision of technical solutions for any issues arising during EPC execution
etc.

Japan


Project Owner

Hokkaido Gas Co., Ltd.

Project Name

Ishikari LNG Receiving Terminal Phase 1 & Phase 2 Project

Completion Date

November 2012 / August 2016

Scope of Work

TGES was awarded the EPC Project as EPC Contractor and successfully completed the Project including :
【Phase 1】
-Jetty and Berth for LNG carriers
- 180,000m³ Above ground full containment LNG storage tank
- LPG spherical tanks
- LNG vaporizers
- Other associated equipment and facilities for gas send-out
【Phase 2】
- 200,000m³ Above ground full containment LNG storage tank
- LPG spherical tanks
- Additional LNG vaporizers

Project Owner

Tokyo Gas Co., Ltd.

Project Name

Hitachi LNG Receiving Terminal Project

Completion Date

March 2016 / March 2021

Scope of Work

TGES was awarded the EPC Project as EPC Contractor and successfully completed the Project including :
【Phase 1】
- 230,000m³ Above ground full containment LNG storage tank
- 50,000m³ Above ground full containment LPG storage tank
- LNG vaporizers
- Other associated equipment and facilities for gas send-out
【Phase 2】
- 230,000m³ Above ground full containment LNG storage tank
- LNG vaporizers